Baikal Mining Company, the operator of the Udokan copper deposit, announces adoption of the new name – Udokan Copper.

Second 220kV HV Power Transmission Line Constructed at Udokan
The second high-voltage power transmission line (double-circuit) extended for 25 km from the substation in Novaya Chara settlement up to Udokan MMP site.

Integral Readiness of Udokan Mining and Metallurgical Plant Construction Project is 40 Percent
This was stated by the Chairman of the Board of Directors of Baikal Mining Company Mr.Valery Kazikaev in the course of the 7th congress of miners held on November 27, 2020 in Moscow.

Construction of the Ore Crushing Building Is Completed at Udokan
At the construction site of the Udokan mining and metallurgical plant, the installation of wall panels and a roof on the crushing body has been completed.

Construction of the Materials & Supply Base is completed at Udokan
At the construction site of the Udokan mining and metallurgical plant, the construction of the building of the Materials and Supply Base has been completed.

A most powerful transformer has been delivered to Udokan site to provide power for mining and processing
A 100MW transformer of over 130 tons has been delivered from Novaya Chara railroad station to the “Bluzhdayuschy” substation construction site.